This is the final week and we have finished our stage and dome project. This past week we had to finish connecting the struts to ...
Read more
These two weeks we attached walls on to the stage by nailing them down, to make it stronger and more stable so the wind wouldn't ...
Read more
We started to sort out the struts and hubs for the dome. Originally the hubs were smaller than they are now, the reason we had ...
Read more
We got our music class at school to test our sound dome and stage. They did a small performance, here it is.... Here is Atama ...
Read more
These two weeks we finished off placing the ply wood then screwing it down. We had to saw off any over hanging pieces of plywood, ...
Read more
We decided to go with the advice our adviser Greg Kelly gave us about laminating an arch to provide support for the rest of the ...
Read more
These weeks we nailed the joists on to the bearers and sawed off the extra overhanging wood on the sides. Some of the joists are ...
Read more
The geodesic dome sound shell plans we originally had weren't that great, so Shontae found this 3D model on sketch-up 3D warehouse. We had to ...
Read more
These two weeks we have finished digging the pile holes and concreted them. We also drilled holes through the bearers and piles to put the ...
Read more
Krystal put a post on the offical ngaruawahia high facebook page to see if anyone had any old fence battens or post to donate for ...
Read more