FLOOR FRAMING UNDERNEATH

We have completed our floor framing after many days of delays due to it being to wet to work outside. We are finally getting into the groove of things and getting some good productive work done. We are now onto our back wall framing, we have decided to check in our studs and knogs to each other and to make the walls 2 meters high. We have scaled down our sheds floor base from 3.0x2.4 to 3.0x1.8 as we felt it would be to large and difficult to transport and would be easier to store. Unfortunately this week Ben and Connor are absent on outdoor education trip so it will just be us three for majority of the week.